Overview

Advisory Circular (AC) 139.V-01, Guidance for vertiport design, is published by Australia's Civil Aviation Safety Authority (CASA). It sits within CASA's aerodrome guidance under Part 139 of the Civil Aviation Safety Regulations 1998 (CASR). It is for people designing and building vertiports to support advanced air mobility (AAM) operations. Vertiports may be in urban or regional locations, or on existing aerodromes. Advisory circulars give advice and illustrate one way of meeting requirements, but not necessarily the only way. They are meant to be read alongside the relevant regulations.

A draft (v1.0) went to public consultation in November 2022, and the first version was published in July 2023. The AC applies to vertiport designers, builders and operators, vertiport proponents, AAM aircraft owners and operators, planning authorities, aerodrome operators and CASA itself.

Aircraft

CASA does not develop aircraft. The v1.0 text gives initial guidance on planning and designing vertiports for VTOL-capable aircraft (VCA) flown with a pilot on board, in visual conditions only. Its basic dimensions are a final approach and take-off area (FATO) of at least 1.5 × Design D and a touchdown and lift-off area (TLOF) of at least 0.83 × Design D. Where the design aircraft's flight manual (AFM) specifies something larger, that applies instead. CASA's companion guide says the TLOF figure comes from heliport recommendations. CASA says it tried to balance outcome-based and prescriptive guidance, keeping specifications flexible because AAM is still developing.

Status

Version 1.1 is the current edition. CASA's advisory circular listing shows it was updated on 7 August 2026. The version history lists changes to section 2.2.3 (downwash and outwash) and to section 3.2.2 and Figure 2 (minimum TLOF size). The revised TLOF value is not confirmed here. A related document, AC 139-10, covers vertical flight facilities at aerodromes designed for aeroplanes and cross-references AC 139.V-01. It was first issued as v1.0 in March 2026, and v1.1 followed in June 2026.

In May 2024 CASA published a plain-English Guide to vertiport design to go with the AC. In December 2024 CASA published its updated RPAS and AAM Strategic Regulatory Roadmap (v2.1, dated January 2025). The roadmap expects AAM operations in Australia, including the first commercial passenger transport in urban areas, to begin between 2027 and 2029.

Academic commentary has described the AC as broad and preliminary, drawing heavily on helicopter standards. On 22 October 2026 the US FAA released its own draft vertical flight infrastructure AC (150/5390-4), with comments due by 11 January 2027.

Asia and Sri Lanka

No direct Sri Lanka link found. No agreements involving CASA and South Asian authorities were confirmed. In August 2026 the Civil Aviation Authority of Sri Lanka (CAASL) adopted EHang's Global Fast Track Programme for a pilotless eVTOL sandbox. The original scope of AC 139.V-01 was limited to piloted aircraft in visual conditions.

Milestones

  • Nov 2022: Draft AC 139.V-01 v1.0 (Guidelines for vertiport design) released for public consultation
  • Jul 2023: AC 139.V-01 v1.0 published as the initial advisory circular
  • May 2024: CASA publishes the plain-English Guide to vertiport design (v1.0, 29 May 2024) to accompany the AC
  • Dec 2024: CASA publishes its updated RPAS and AAM Strategic Regulatory Roadmap (v2.1, dated 01/2025), expecting AAM operations in Australia to begin between 2027 and 2029
  • Mar 2026: AC 139-10 v1.0 (vertical flight facilities at aerodromes designed for aeroplanes) initial issue
  • Jun 2026: AC 139-10 v1.1 published; it cross-references AC 139.V-01
  • Aug 2026: AC 139.V-01 v1.1 published (updated 7 August 2026), revising downwash/outwash and minimum TLOF size guidance