At a glance
- Screening grade
- C
- District
- Galle
- Planner score
- 69/100
- Airspace
- none
- Residents within 2 km
- 25,118
- Departure headings
- 270° / 90°
- Coordinates
- 6.4310, 79.9960
Summary
This candidate point is on the Bentota River in Galle District, Southern Province. The data shows water at the point (95% water occurrence), so that is the headline constraint. The design reference used here (FAA EB 105A) covers land-based vertiports only. It excludes float and amphibian aircraft. A vertiport here would need suitable land on the bank or a floating platform accepted by the Civil Aviation Authority of Sri Lanka (CAASL). The dataset also gives an on_land flag of true, which conflicts with the water land cover. The exact pad position therefore needs to be confirmed.
Away from that issue, the desk-level picture is reasonable. The site is outside listed controlled and restricted airspace. Terrain is flat. Winds are moderate. The Bentota tourism node is 1.1 km away. Our judgement is grade C: there is a demand case, but the footprint is unresolved.
Location and catchment
The site is 1.1 km from Bentota (tourism). In the source data the point is listed as a Cinnamon Air destination (code BJT, from OurAirports). Resident population is 2,581 within 500 m, 25,118 within 2 km and 237,013 within 10 km. These are night-time residents, so hotel guests and daytime visitors are not counted. Night-light radiance is 4.0.
Aluthgama Hospital is 704 m away and Bentota Hospital 908 m away. Teaching Hospital Kalutara (Nagoda) is 14.8 km away, inside the EH216-S practical range of about 24 km. Port City Colombo is 59.0 km away, which is well beyond the range of the type now being tested.
Airspace
The data places the site in no listed airspace class. The nearest features are:
- the Katukurunda light-aircraft training area (VCT-D), 2.7 km away
- the Katukurunda CTR, 4.5 km away.
The Katukurunda airfield is 13.8 km away. No prohibited or restricted area is listed. Sri Lanka has not yet published a vertiport standard, so CAASL would decide the terms. Because the training area is so close, coordination with light-aircraft traffic is likely to be needed.
Approach paths and terrain
Our convention: headings are the directions the aircraft flies when departing, and the approach on each path is the reciprocal.
The 8:1 terrain check sampled the 200 m elevation model along 16 headings out to 1,219 m. It found no terrain penetration on any heading. Clearance was 12 m on 15 headings and 2 m on 112.5°, with the minimum in each case at 100 m. Site elevation is 0 m, and the maximum slope within 500 m is 1.5°.
We propose:
- Primary departure heading: 270°. This is into the steady south-west monsoon wind from 268°, and close to the October–November wind from 282°.
- Secondary departure heading: 090°. This is the reciprocal of the primary.
Heading 112.5° has the smallest terrain margin, so we have avoided it. The check ignores buildings, trees, towers and power lines. Within 500 m, tree cover is 33% and built-up land is 25%. These could penetrate the surfaces even where terrain does not.
Space and layout
Under EB 105A, the Safety Area for the largest Reference Aircraft is about 38 m × 38 m (≈1,450 m²). That is before taxiways, parking, charging and a passenger area. A ministry figure gives under 900 m² per pad for a 2-seat EH216-S class vertiport. The point itself is water and 42% of the area within 500 m is water, so the options are:
- bank-side land next to the river, or
- a floating or pontoon platform, which is outside the EB's land-based scope.
Built-up cover in the site cell is 13%. The data does not show who owns the land or whether it is available.
Wind and weather
ERA5 data for 2015–2024 shows:
| Season | Prevailing wind from | Steadiness | Mean daily max wind | Days with gusts >15 m/s | Days with rain >20 mm |
|---|---|---|---|---|---|
| SW monsoon (May–Sep) | W, 268° | 0.85 | 4.4 m/s | 4.8% | 7.8% |
| NE monsoon (Dec–Feb) | SE, 129° | 0.08 | 2.2 m/s | 0% | 6.0% |
| Mar–Apr | S, 184° | 0.42 | 2.6 m/s | 0% | 4.8% |
| Oct–Nov | WNW, 282° | 0.36 | 3.2 m/s | 1.3% | 15.7% |
No season shows gusts above 20 m/s. Mean monthly rainfall is highest in October–November (420 mm), then 250 mm in the SW monsoon and 245 mm in March–April. ERA5 has a resolution of about 25–30 km. It will smooth out local sea-breeze effects and wind channelling along the river.
Environment and neighbours
The data shows no protected area at or near the site. OpenStreetMap shows one unnamed place of worship 434 m away, no schools within 500 m and no heritage features within 1 km. OSM coverage is incomplete. With 2,581 residents within 500 m, noise and the downwash/outwash caution area matter. FAA research measured outwash above 55.5 km/h at 38.5 m from the pad centre for some designs. Riverbank ecology and river users are not covered by the data.
What would need to be checked
- Whether bank land is available and big enough, or whether CAASL would accept a floating platform.
- Which pad position explains the conflict between the on_land flag and the water land cover.
- An obstacle survey of trees, buildings and masts along the 090° and 270° paths.
- Coordination with the Katukurunda training area and CTR.
- Flood levels and how river levels vary at the pad.
- A local wind survey, plus noise and outwash planning for nearby residents.
- Environmental and riverbank consents.
This is a desk-based planning screen using open data, not an approval, survey or design.
Scorecard
| Criterion | Rating | Evidence |
|---|---|---|
| Demand and catchment | 3/5 | The Bentota tourism node is 1.1 km away. There are 2,581 residents within 500 m, 25,118 within 2 km and 237,013 within 10 km. These are night-time resident counts, so visitors are not included. |
| Airspace | 4/5 | The site is not inside any listed controlled, restricted or prohibited airspace. The Katukurunda light-aircraft training area (VCT-D) is 2.7 km away and the Katukurunda CTR is 4.5 km away, so coordination will be needed. |
| Terrain and approach paths | 4/5 | The 200 m model found no terrain penetration of the 8:1 surface on any of the 16 headings. Minimum clearance is 12 m on 15 headings and 2 m on 112.5°. Buildings and trees are not modelled. |
| Footprint and land | 2/5 | Land cover at the point is water, with 95% water occurrence and 42% water within 500 m. The on_land flag says true, which conflicts with this. A land-based pad (under 900 m² per pad for an EH216-S class vertiport, or a Safety Area of about 1,450 m² for the largest Reference Aircraft, before taxiways and parking) would need bank land or a platform. |
| Wind and weather | 4/5 | In the SW monsoon the wind blows from the W (268°) with steadiness 0.85 and a mean daily maximum of 4.4 m/s. Gusts exceed 15 m/s on 4.8% of days and never exceed 20 m/s. October–November averages 420 mm of rain a month, with 15.7% of days above 20 mm. |
| Environment and protected areas | 4/5 | The site is not in a protected area, and the data lists no nearby protected areas. The river setting and the 33% tree cover within 500 m may still bring ecological and riverbank questions. |
| Noise and neighbours | 3/5 | 2,581 residents live within 500 m and built-up land makes up 25% of that area. OSM shows one place of worship at 434 m and no schools within 500 m. |
| Connectivity and emergency value | 3/5 | Aluthgama Hospital is 704 m away and Bentota Hospital 908 m away. Teaching Hospital Kalutara (Nagoda) is 14.8 km away, inside the EH216-S practical range of about 24 km. Port City is 59.0 km away, well beyond that range. |
Key risks
- The screened point is on water (95% water occurrence). The design reference covers land-based sites only, so it needs bank land or a floating platform that the authority accepts.
- The data conflicts: on_land is true, but land cover is water. The exact pad location is unresolved.
- The Katukurunda training area is 2.7 km away and the Katukurunda CTR 4.5 km away, so traffic coordination with light aircraft will be needed.
- Trees (33% within 500 m) and buildings (25%) are not in the 8:1 terrain check and could penetrate the approach surfaces.
- October–November is wet, averaging 420 mm a month with 15.7% of days above 20 mm, which reduces VFR availability.
- There are 2,581 residents within 500 m, so the outwash caution area and noise need careful siting.
Open questions
- Is there bank-side land of at least about 900–1,450 m² next to the river point, and who controls it?
- Would CAASL accept a floating or pontoon platform, and under what standard?
- Which pad position explains the data conflict between on_land = true and water land cover?
- What heights do trees, buildings, masts and power lines reach along the 090° and 270° paths and their transitional surfaces?
- What coordination is required with the Katukurunda training area and CTR operators?
- How does the river behave in flood, given October–November rainfall, and what are the level changes at the pad?
- Are there riverbank, fisheries or ecological consent requirements for the water body?
- What would a local wind survey show about the sea-breeze effects that ERA5 smooths out?
Desk-based planning screen using open data (routes.evtol.lk planner layers, OpenStreetMap, ERA5 2015–2024) and the FAA Engineering Brief 105A as a design reference. It is not a survey, design or approval; Sri Lanka has not published a vertiport standard. Drafted with an AI model constrained to the data, then independently fact-checked.