At a glance
- Screening grade
- C
- District
- Hambantota
- Planner score
- 51/100
- Airspace
- none
- Residents within 2 km
- 12,695
- Departure headings
- 270° / 68°
- Coordinates
- 5.9902, 80.7331
Summary
The main constraint at Mawella Lagoon is the ground itself. The site is on the lagoon edge. The data marks the point as on land, but the cell is water 68% of the time. Within 500 m the land cover is 39% water and 11% herbaceous wetland. The site cell itself is tree cover.
The airspace is uncomplicated. The site is not inside any listed controlled, restricted or prohibited area. Terrain is low and level. Demand is modest, and the site is far from any other node. On current information we grade it C: a possible tourism stop if a dry, firm and cleared pad can be confirmed.
OurAirports lists the point as a Cinnamon Air destination (code DIW). This report treats it as a candidate vertiport only.
Location and catchment
The site is near Dickwella in Hambantota District, Southern Province, at 0 m elevation. Resident populations are:
- 658 within 500 m
- 12,695 within 2 km
- 143,696 within 10 km
These are night-time resident counts and do not include visitors. Night-light radiance is low at 0.8.
The nearest tourism cluster is Tangalle / Hiriketiya, 7.9 km away. Base Hospital Tangalle is also 7.9 km away, and OpenStreetMap lists no hospitals within 3 km.
Our judgement is that the main case is tourism. Resident demand and medical value are limited.
Airspace
The airspace grid shows no class for this location, and the site is not inside any listed area. The nearest airspace features are:
- the Mattala CTR (including the former Wirawila CTR), 35.8 km away
- restricted area VCR20 (Diyatalawa Army camp), 91.32 km away
The nearest airport is Koggala, 45.7 km away. Sri Lanka has not published a vertiport standard, so CAASL would still need to set the conditions for any operation.
Approach paths and terrain
The 8:1 terrain check sampled 16 headings on a 200 m elevation model. No terrain penetration was found on any heading. Minimum clearance was 12 m at 100 m on 15 headings, and 8 m at 300 m on 315°.
These margins are small. The model ignores trees, buildings, towers and power lines. Tree cover makes up half the land within 500 m. In our judgement, trees could penetrate the lower part of the surfaces. None of the paths should be treated as obstacle-free.
Heading convention: headings are the direction flown on departure; the approach path is the reciprocal.
- Primary heading: 270°. This points into the SW-monsoon wind (from 262°) and the October–November wind (from 269°).
- Secondary heading: 068°. This points into the NE-monsoon wind (from 60°).
The two headings are 157.5° apart. We have not used 315°, which had the lowest terrain margin.
Space and layout
The site cell is 0% built. Slope is 2.5° at the site and 2.3° on average within 500 m, with a maximum of 9.5°.
For the largest Reference Aircraft in FAA EB 105A, the Safety Area is about 38 m × 38 m (about 1,450 m²). This excludes taxiways, charging and the passenger area. A ministry figure gives under 900 m² per pad for an EH216-S class vertiport.
EB 105A also requires a ground-level Safety Area that prevents loose debris and has controlled drainage. On a lagoon edge that floods often, this would need engineering.
The reference aircraft in EB 105A is land-based. Float and amphibian aircraft are excluded. A water-based operation would therefore fall outside the main design reference used here.
Wind and weather
The ERA5 statistics come from a point 6.2 km away. ERA5 has a coarse grid of about 25–30 km.
| Season | Wind from | Steadiness | Mean daily max wind | Days with gusts over 15 m/s |
|---|---|---|---|---|
| SW monsoon (May–Sep) | 262° | 0.95 | 6.8 m/s | 14.8% |
| NE monsoon (Dec–Feb) | 60° | 0.69 | 4.6 m/s | 1.3% |
| Mar–Apr | variable | 0.17 | 4.2 m/s | 0.0% |
| Oct–Nov | 269° | 0.48 | 4.7 m/s | 3.0% |
The NE monsoon blows mainly from the ENE. In March and April the wind direction is very variable.
Monthly rainfall is 110–125 mm in most seasons. It rises to 245 mm in October–November, when 8.4% of days have more than 20 mm.
ERA5 smooths out local effects. Sea breezes and flow off the lagoon and trees could create turbulence that the data cannot show.
Environment and neighbours
The site is not in a WDPA protected area. The nearest protected area is Dandeniya Aparakka Reserved Forest, 10.25 km away. However, water and wetland make up half of the area within 500 m. In our judgement, lagoon ecology deserves specific review.
OpenStreetMap shows:
- one unnamed place of worship at 283 m
- no schools within 500 m
- no heritage features within 1 km
OpenStreetMap coverage is incomplete, so these counts may be low. Outwash from some designs can exceed 55.5 km/h at 38.5 m from the pad, so a downwash caution area would be needed. Within it, people, boats and loose material must be kept clear during operations.
What would need to be checked
- A ground and flood survey to find a dry, firm pad area.
- The intended operating mode (land or water) and the standard that would apply.
- Tree, structure and power-line heights under the 270° and 068° surfaces.
- Ecological assessment of the lagoon and wetland.
- CAASL conditions and coordination with the Mattala CTR.
- Land ownership and access.
- Local wind measurement.
- Visitor demand and the aircraft range needed to link the site to a network. Port City is 144.2 km away, far beyond the roughly 24 km practical range of the EH216-S now on test.
This is a desk-based planning screen using open data, not a survey, design or approval.
Scorecard
| Criterion | Rating | Evidence |
|---|---|---|
| Demand and catchment | 2/5 | There are 658 residents within 500 m, 12,695 within 2 km and 143,696 within 10 km. Night-light radiance is low at 0.8. The nearest tourism cluster (Tangalle / Hiriketiya) is 7.9 km away. |
| Airspace | 5/5 | The grid shows no airspace class and the site is not inside any listed area. The nearest controlled airspace is the Mattala CTR, 35.8 km away. The nearest restricted area (VCR20) is 91.32 km away. |
| Terrain and approach paths | 3/5 | The 200 m terrain model shows no penetration of the 8:1 surface on any of the 16 headings. Minimum clearance is 12 m at 100 m on 15 headings and 8 m at 300 m on 315°. The margins are small. Trees, which make up 50% of land cover within 500 m, are not in the model. |
| Footprint and land | 2/5 | The site cell is 0% built, with 2.5° slope and tree cover. However, water occurrence is 68%, and the 500 m mix is 39% water and 11% herbaceous wetland. A dry, firm surface for a pad is not shown by the data. |
| Wind and weather | 3/5 | The SW monsoon wind blows from 262° with 0.95 steadiness. On 14.8% of SW-monsoon days gusts exceed 15 m/s. October–November rainfall is 245 mm per month, with 8.4% of days over 20 mm. The ERA5 values are taken from a point 6.2 km away. |
| Environment and protected areas | 3/5 | The site is not in a WDPA protected area. The nearest is Dandeniya Aparakka Reserved Forest, 10.25 km away. Lagoon water and wetland make up half of the 500 m area, so ecological sensitivity needs checking. |
| Noise and neighbours | 3/5 | There are 658 residents within 500 m. OpenStreetMap shows one unnamed place of worship at 283 m, no schools within 500 m and no heritage features within 1 km. |
| Connectivity and emergency value | 2/5 | The nearest hospital, Base Hospital Tangalle, is 7.9 km away, and OpenStreetMap lists no hospitals within 3 km. Koggala airport is 45.7 km away and Port City is 144.2 km away, well beyond the roughly 24 km practical range of the EH216-S. |
Key risks
- Wet ground: the site cell is water 68% of the time and is close to the lagoon. The ground may flood or be soft, and a float/amphibian operation falls outside the EB 105A reference aircraft scope.
- Tree cover (50% within 500 m) could penetrate the low early part of the 8:1 surfaces. Terrain clearance there is only 8–12 m.
- The demand case is thin: low night lights (0.8), a modest resident catchment, and the tourism cluster 7.9 km away rather than at the site.
- The site is isolated from any network: Koggala is 45.7 km away and Port City is 144.2 km away, both beyond current sandbox aircraft range.
- SW-monsoon gusts exceed 15 m/s on 14.8% of days, and October–November rainfall is heavy (245 mm per month).
- Downwash and outwash near open water, wetland and an unnamed place of worship 283 m away.
Open questions
- Is there a dry, firm, non-flooding area large enough for a Safety Area of about 38 m × 38 m, or under 900 m² for an EH216-S class pad? This needs a ground survey and flood history.
- Is a water-based (waterdrome) operation intended? If so, which standard and which aircraft type would apply, given that EB 105A excludes float and amphibian aircraft?
- Tree heights and any buildings, masts or power lines under the 270° and 068° approach and departure surfaces.
- The ecological status of the lagoon and wetland, and whether an environmental assessment is needed.
- CAASL requirements for operating outside controlled airspace and coordinating with the Mattala CTR.
- Land ownership, access and the existing use at the 'Cinnamon Air destination' point (DIW) recorded in OurAirports.
- Local wind measurements to check sea-breeze and lagoon effects that the coarse ERA5 data smooths out.
- Visitor demand from the Tangalle / Hiriketiya area and which aircraft range would make a route viable.
Desk-based planning screen using open data (routes.evtol.lk planner layers, OpenStreetMap, ERA5 2015–2024) and the FAA Engineering Brief 105A as a design reference. It is not a survey, design or approval; Sri Lanka has not published a vertiport standard. Drafted with an AI model constrained to the data, then independently fact-checked.